Frontenac Howe Islander Docks Rehabilitation - Update
The County of Frontenac received updated information from the contractor regarding construction timelines and scheduled service interruptions related to the Frontenac Howe Islander.
- The next full closure is scheduled from Monday, May 11 at 10 pm to Thursday May 14th at 2 pm.
- Two further closures will be required in May to complete the work: Monday, May 18th from 10 pm to Thursday, May 21st at 2 pm; and Monday, May 25th from 10 pm to Thursday, May 28th at 2 pm.
- The work, originally scheduled for completion before April 30, is now forecasted for completion in mid-June.
- The contractor has set aside 56 hours for each remaining full closure to include time to adapt to weather events or other unforeseen circumstances. If work concludes early, service will resume early.
- This work involves the rehabilitation of the ferry docks at both the island and mainland sides.
- A mainland detour route is provided and delineated by detour signage.
- The Township three-car ferry will remain in extended operation during closures to ensure passage on and off the island.
- The island-side parking area is closed for the duration of the project to ensure the dry hydrant, boat launch, and private laneways remain unobstructed by construction activities and equipment.
The remaining planned ferry service interruptions are:
64-hour full closures:
- Monday, May 11th from 10 pm to Thursday, May 14th at 2 pm
- Monday, May 18th from 10 pm to Thursday, May 21st at 2 pm
- Monday, May 25th from 10 pm to Thursday, May 28th at 2 pm
As always, unforeseen circumstances may necessitate changes to this schedule. Further full closures may be required to complete the work. We will keep you apprised of any new developments as soon as they emerge.
This is a coordinated effort among MTO, contractor, Township, and County staff. Your patience and understanding is appreciated.