Update related to the Howe Island County Ferry docks rehabilitation project
Received from the County of Frontenac:
By way of reminders and update related to the Howe Island County Ferry docks rehabilitation project:
-
We received word today that the next full closure is now scheduled from this Tuesday, May 19 at 6 am to Friday, May 22 at 6 am.
- One subsequent closure is scheduled to complete the work: Monday, May 25th from 10 pm to Thursday, May 28th at 2 pm.
- The work is forecasted for completion in mid-June.
- The contractor has set aside 64 hours for each remaining full closure to include time to adapt to weather events or other unforeseen circumstances. If work concludes early, service will resume early.
- This work involves the rehabilitation of the ferry docks at both the island and mainland sides.
- A mainland detour route is provided and delineated by detour signage.
- The Township three-car ferry will remain in extended operation during closures to ensure passage on and off the island.
- The island-side parking area is closed for the duration of the project to ensure the dry hydrant, boat launch, and private laneways remain unobstructed by construction activities and equipment.
The remaining planned ferry service interruptions is:
- Monday, May 25th from 10 pm to Thursday, May 28th at 2 pm
As always, unforeseen circumstances may necessitate changes to this schedule. Further full closures may be required to complete the work. We will keep you apprised of any new developments as soon as they emerge.
This is a coordinated effort among MTO, contractor, Township, and County staff. Your patience and understanding is appreciated.